Timeline of LHC Run 3 Measurements in 2025

This page provides quick access links to logbook entries of important OMC shifts or measurements done during the LHC 2025 commissioning and MDs. Some entries (underlined) offer a tooltip when hovered, with a quick description of the important information from that entry. The tables below can be sorted by clicking next to the column headers.

Results Visualization

Various results graphs and the scripts to make them are available in lintrack:

/afs/cern.ch/eng/sl/lintrack/LHC_commissioning2025/

Start Date End Date Shifts Type Shift Purpose Logbook Link
2025-04-08 14:00 2025-04-09 00:30 0.5W 0.7WN Commissioning Injection Optics Global Corrs Shift Start / Summary ()
2025-04-09 15:30 2025-04-10 03:00 0.4W 1.1WN Commissioning Coupling Through Squeeze + dE/E Shift Start / Summary ()
2025-04-11 18:00 2025-04-12 09:00 1.9HN Commissioning Injection and Ramp Shift Start / Summary ()
2025-04-13 08:00 2025-04-13 16:00 1H Commissioning Measurements through the Squeeze Shift Start / Summary ()
2025-04-18 11:15 2025-04-18 23:19 1.5H Commissioning ADTtests, phaseknob, 60cm AbA coupl, 18cm optics Shift Start / Summary ()
2025-04-19 16:40 2025-04-20 03:30 0.4H 1HN Commissioning Energy Shift, NL at 18cm and local iterations Shift Start /
2025-04-20 16:00 2025-04-20 23:00 0.2H 0.65HN Commissioning NL at injection, IRNL 18cm Shift Start / Summary ()
2025-04-21 17:30 2025-04-22 06:00 1.6HN Commissioning IRNL 1.2m and 18cm Shift Start / Summary ()
2025-04-24 13:00 2025-04-25 03:30 0.6W 1WN Commissioning Global Corrs at 60cm and 18cm and Validation Shift Start / Summary ()