2025-03-18 14:00 | 2025-03-18 18:00 | 0.5W | Commissioning | Panos/Ewen/Josch/Mattia | optics commissioning - weird total phase | Start |
2025-03-19 16:00 | 2025-03-19 19:00 | 0.5W | Commissioning | Panos/Ewen | optics commissioning - weird total phase | Start / Summary |
2025-03-26 12:00 | 2025-03-26 15:00 | 0.5W | MD | Panos | ACD with fixed BPM issues | Start |
2025-07-25 14:00 | 2025-07-25 19:00 | 0.5W | MD | Panos/Ewen | optics measurement tests with kicks | Start |
2025-07-29 09:00 | 2025-07-29 12:00 | 0.5W | MD | Panos | optics measurement tests with kicks | Start |
2025-08-05 14:00 | 2025-08-05 20:00 | 0.5W | MD | Panos | optics measurement tests with kicks | Start |
2025-09-09 22:00 | 2025-09-10 01:00 | 0.5WN | MD | Panos/Ewen/Rogelio | CrabCavity optics measurements | Start |
2025-09-17 15:00 | 2025-09-17 18:00 | 0.5W | MD | Panos/Ewen | Tests of CC measurement procedures | Start |
2025-09-19 09:00 | 2025-09-19 13:00 | 0.5W | MD | Panos | Tests of CC measurement procedures | Start |
2025-09-23 09:00 | 2025-09-23 13:00 | 0.5W | MD | Panos/Mattia | Tests of CC measurement procedures | Start |